The Africa Water Investment Pipeline

Welcome to the Africa Water Investment Pipeline, a strategic portfolio of over 80 transformative water and climate-resilient infrastructure projects from across the African continent.

This pipeline will be showcased during the 2025 AU- AIP Africa Water Investment Summit in Cape Town, serving as a launchpad for investment, partnerships, and progress.

The pipeline represents a diverse and dynamic portfolio with a total project cost exceeding USD 30 billion. The projects span all stages of development, from early concept to those already under construction. The initiatives cover a wide range of subsectors including water supply and sanitation, multipurpose infrastructure, flood management, early warning systems, aquaculture, integrated water resources management (IWRM), nature-based solutions, traditional knowledge and conflict management, energy and energy efficiency, and water transport. This platform not only provides visibility for these projects, but also facilitates structured engagement opportunities for investors and partners to connect with project owners.

This marks the beginning of a long-term investment journey, with select high-impact projects set to be fast-tracked for presentation at other similar platforms. A second AU, AIP Water Investment Summit will be held in 2027/2028 to assess progress and spotlight new flagship projects. This rolling pipeline is fully aligned with the Africa Water Investment Action Plan and the AIP Framework, with a clear focus on delivering impact through 2030.

PROJECT PIPLINE

wdt_ID wdt_created_by wdt_created_at wdt_last_edited_by wdt_last_edited_at PROJECT NAME PIPELINE COUNTRY/REGION SUB-SECTOR BUDGET ASK STATUS MORE INFO PROJECT FICHE
1Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMAfDB Opportunities for cofinancingAfrica Water FacilityContinentalAll sub-sectorsUSD 2.1 billionUSD 1.9 billionConcept Notes developed
2Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMAlgoa Water Supply System Coerney DamSouth Africa Department of Water and SanitationSouth Africa/ Eastern CapeRaw Water Resources$40m$40mThe design work is currently underway and is at 18% complete.
3Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMAngololo Water Resources Development ProjectProgramme for Infrastructure Development in Africa (PIDA)Kenya and UgandaIrrigation/Water Supply$132m$132mPre-feasibility study and feasibility study undertaken; Requires project structuring
4Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMArtificial aquifer recharge in the Souss Massa basinNationalMoroccoWater Supply, Irrigation$36m$36mPreparing calls for tender
5Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMAWF Investment Opportunities PortfolioAfrican Water FacilityContinentalAll sub-sectorsEUR 2.6 billionEUR 2.6 billionInvestment Ready Projects / Master Plans / Ongoing preparation phase / Co - development
6Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMBugesera Feacal Slugde Treatment Plant (FSTP)Water and Sanitation CorporationRwandaSanitation$5.2m$5.2mDetailed design completed
7Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMChirundu Water Supply and Sanitation Project Phase 1SADC Water Fund PipelineZambia & ZimbabweWater Supply$8.3m$8.3mPre-feasibility study and feasibility study Completed; Implementation Ready
8Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMClimate Resilient SDG6 Water System UtilisationNationalGhanaWater SupplyUSD17mUSD17mConcept Note approved; Environmental & Social Impact Assessment (ESIA) & ESMP underway (due Aug 2025); AfDB appraisal mission scheduled Q4 2025.
9Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMClimate-resilience through enhanced co-production for climate information and early warning systems in GhanaAU AIP Multi-country GCF Readiness ProjectGhanaCIEWS for WEF Nexus$60m$60mConcept Note being developed
10Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMClimate-Resilient Water, Sanitation, and Flood Management ProjectNationalMalawiWater Supply and Sanitation, Flood Management$30m$27mResource Mobilisation
11Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMCongo River Water Transfer and Hydropower Project to Zambezi Water Transfer Project (C – ZAMB. WTP) Feasibility StudySADCDemocratic Republic of Congo and Riparian CountriesWater Supply and Energy$20m$20mPrefeasibility study
12Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMConstruction of 60-Megawatt Independent Solar Power Plant for Blantyre Water BoardNationalMalawiWater Supply and Sanitation, Energy$75m$72mDetailed Project Report, completed in March 2024, Project sites acquired
13Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMConstruction of a dam on the river Zio to improve drinking water supply to the city of Lome-TogoNationalTogoWater Management, Climate Adaptation, Capacity Building$319.5m$319.5mFeasibility and hydrogeological studies
14Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMCrocodile East Water Project (CEWP)South Africa Department of Water and SanitationSouth Africa, Eswatini and MozambiqueWater SupplyZAR 5 billionZAR 5 billionFeasibility 2023 -2026. Detailed design and funding arrangement 2027 – 2029. Construction 2030 - 2033
15Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMDrinking Water Supply (AEP) for the cities of Ouahigouya and SéguénégaNationalBurkina FasoWater Supply$88m$88mConcept Note
16Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMDrinking water supply project for the towns of Imasgho, Kindi, Ténado, Kokologho, Bama, and Pa using a new systemNationalBurkina FasoWater Supply$23m$22mConcept Note
17Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMEmpowering Women-Led Drone Enterprises for Water-Efficient Agriculture and Livelihood Diversification in ZimbabweNationalZimbabweWater Supply, Sanitation, Irrigation, Flood Management$40m$28mConcept Note
18Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMEnhancing Climate Resilience through Integrated Flood Management of the Nyamwamba River Catchment in Kasese District NationalUgandaFlood Management, Ecosystem-based Adaptation$74.7m$74.7mEngineering designs completed (2025); implementation planned for July 2026
19Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMEnhancing Energy Efficiency in Water Utilities through Targeted Audits and Technology UpgradesNationalGhanaWater Supply and Energy Efficiency$3.5m$3.5mConcept Note
20Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMExpansion and Improvement of Water Supply and Sewerage Services in Lilongwe CityNationalMalawi$38m$38mPreliminary Design
21Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMExpansion of water supply from Saua-Saua_Expansion of water supply through Lurio River and the related water supply infrastructures.NationalMozambiqueWater Supply$354.5m$354.5mTechnical, Environmental and financial and economic Pre-feasibilities studies
22Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMExtension of the wastewater collection network and construction of a wastewater treatment plant in greater LomeNationalTogoSanitation$134m$134mFeasibility
23Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMFloating PV Solar Generating Facilities on Katse & Mohale DamLesotho Highlands Development AuthorityLesothoEnergy$305m$305mPre-Feasibility – complete Detailed Feasibility Studies – Development of Terms of Reference in progress
24Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMFlood control infrastructure in the Middle and Upper Bani regions to strengthen the resilience of local communities and ecosystems to the impacts of climate changeAU AIP Multi-country GCF Readiness ProjectMaliFlood Management – protection Agriculture and supporting watershed ecosystems$29.4m$2.5mConcept Note being developed
25Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMFoxwood DamSouth Africa Department of Water and SanitationSouth Africa/ Eastern CapeRaw Water Resources$140m$140mProcurement of professional service provider for design stage underway
26Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMGAFA -Water Investment Projects Pipeline for the Horn of AfricaUnited Nations Development ProgrammeKenya, Ethiopia, Somalia, Sudan, South Sudan, Eritrea, Djibouti and UgandaWater supply, sanitation, irrigation, livestock, ecosystems, industry, tourism$2Bln$2BlnFinal stage of development and now looking for investment to cover some projects components that respond to the investors interests and governments priorities.
27Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMGlassblock Bopoma Dam and Pipeline ProjectGGF AfricaZimbabweMultipurpose$99.2m$99.2mESIA to be completed September 2025
28Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMGotheye -Téra multi-center drinking water supply project from the River Niger at Farié in the commune of GotheyeNationalNigerWater Supply$350m$300mTender Documents prepared
29Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMGreater Bulwer Bulk Water Supply SchemeSouth Africa Department of Water and SanitationSouth Africa, Kwa-Zulu Natal (Harry Gwala District Municipality)Bulk Water SupplyZAR 3BlnZAR 3BlnImplementation Readiness Study (Bankable Feasibility Study) underway
30Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMGreater Mangaung Water Augmentation Project – Xhariep PipelineSouth Africa Department of Water and SanitationSouth AfricaBulk Water Supply ServiceZAR38.9 BlnZAR38.9 BlnOnce IA is appointed Detail Design can commence.
31Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMGroot Letaba River Development Project (GLeWAP): Nwamitwa DamSouth Africa Department of Water and SanitationSouth AfricaWate Supply and Irrigation$416m$416mPre-construction
32Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMImplementation and operationalization of a water information system for the Agneby basinNationalCote d'IvoireIWRM$12m$12mFeasibility and environmental studies conducted
33Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMInhambane Municipality urban sanitation, drainage and solid waste managementAfrica Water FacilityMozambiqueSanitation and Solid waste management€24 m€24 mInvestment ready
34Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMIntegrated Climate-Resilient Water Resource Hubs for Health, Sanitation, and Food Security in ChadAU AIP Multi-country GCF Readiness ProjectChadClimate-resilient IWRM and WASH$25m$25mConcept Note being developed
35Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMIntegrated Water Security Programme for Salima and Dowa Town Centres_ Chezi, Mvera and ChipokaNationalMalawiWater Supply and Sanitation$50.2m$50.2mDetailed design available; implementation planned for April 2026–December 2027
36Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMIntegration of Gender-Sensitive Agroecological Practices for Community Resilience to the Effects of Climate Change (PIPAG-RCC- Nkingira)AU AIP Multi-country GCF Readiness ProjectBurundiClimate resilient infrastructure to protect water access and sources$22m$22mConcept Note being developed
37Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMKazungula Water Supply and Basic Sanitation Project (Phase II)SADC Water Fund PipelineZambiaWater & Sanitation€3.5m€3.5mImplementation Ready – Completed feasibility. Preliminary and Detailed designs & Tender Dossier completed for Extension of distribution network and Sanitation
38Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMKirehe Water Supply ProjectWater and Sanitation CorporationRwandaWater Supply$46m$46mFeasibility study and Detailed design complete
39Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMKuban Hydroagricultural Dam Construction ProjectNationalCote d'IvoireIrrigation$5m$5mTechnical and environmental studies conducted
40Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMLake Victoria Mediterranean Sea Navigational Line (VICMED) Programme for Infrastructure Development in Africa (PIDA)Egypt, Sudan, South Sudan, Uganda, Burundi, Rwanda, DRC, Ethiopia, Kenya, Tanzania (Basin Countries)Transport and Water$12 Bln$15.7mFeasibility Study Phase 2 – Part 1 ongoing (to be completed by 2026)
41Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMLesotho Highlands Water Project Phase II Scheme - OxbowLesotho Highlands Development AuthorityLesothoMultipurpose$1.5Bln$1.5BlnEngineering Design Phase Environmental Impact and Social Assessment (ESIA)
42Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMLesotho-Botswana Water Project (L-BWT)Programme for Infrastructure Development in Africa (PIDA)Lesotho, South Africa and BotswanaWater Supply, Irrigation, Hydropower€2.3Bln$4.93mFeasibility underway
43Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMLimpopo Transboundary Ecosystem-Based Water Security and Climate AdaptationLimpopo Watercourse CommissionBotswana, Mozambique, South Africa, ZimbabwePayment for Ecosystem Services, Watershed Management, Multipurpose$25m$25mPre-Feasibility complete, moving toward full proposal development
44Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMLomahasha Namaacha Transboundary Water Supply – Phase 2 (Water Treatment Plant and Reticulation)SADC Water Fund PipelineSwaziland & MozambiqueWater Supply€15m€15mImplementation Ready - Completed Update of Feasibility re-scoped components Completed
45Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMLower Songwe Dam, Hydropower Plant and Transmission Lines ProjectAIP Investment Action PlanTanzania, MalawiTransboundary Water Project - Multi-purpose$851.1m$851.1mPre-feasibility study, Feasibility study, Project structuring undertaken
46Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMLusaka City Water Supply Improvement ProjectAfrica Water FacilityZambiaWater Supply$ 205m$ 205mInvestment ready
47Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMLusikisiki Regional Water Supply Scheme_Zalu DamSouth Africa Department of Water and SanitationSouth Africa/ Eastern CapeRaw Water Resources$62m$62mThe design work is currently underway and is at 77% complete.
48Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMMalawi Integrated Water Resilience and Circular Economy Project (MIWR-CE) - Scaling Up Climate Resilient Water Security, Sanitation and Waste to Resource Solutions through Integrated AdaptationAU AIP Multi-country GCF Readiness ProjectMalawiAgriculture and Forestry Protection through Sustainable Land Management$50m$2.5mConcept Note being developed
49Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMMandlakazi Regional Water Supply SchemeSouth Africa Department of Water and SanitationSouth AfricaBulk Water Services Infrastructure DevelopmentZAR 2.4BlnZAR 2.4BlnConstruction
50Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMMbabane Manzini Corridor Multipurpose DamAfrica Water FacilityEswatiniIntegrated water resource management and irrigation$ 55 m$ 55 mInvestment ready
51Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMMusina Beitbridge Bulk Water SupplySouth Africa Department of Water and SanitationSouth Affrica - LimpopoBulk Water Services Infrastructure DevelopmentZAR 2BlnZAR 2BlnDWS has appointed DBSA as IA for planning and implementation of the project, including sourcing external funding. Still in the process of appointing a PSP to undertake bankable feasibility studies, as project will also require exploring private funding.
52Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMNature Based Flood Adaptation to Increase Community Resilience in Rubyiro Catchment-RWBRwanda Water Resources BoardRwandaFlood Management$22m$13mImplementation
53Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMNoordoewer Vioolsdrift Dam (NVD)Programme for Infrastructure Development in Africa (PIDA)Namibia and South AfricaWater Resources$231$1mPre-feasibility study and Feasibility study undertaken, requires ESIAs to be undertaken.
54Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMNorthern Region Water Board_Chilumba Water Supply and Sanitation Project_Northern Region Water BoardNationalMalawiWater Supply and Sanitation$41.6m$41.6mDetailed designs prepared, ESIA and Climate Risk Assessment Report Submitted to Malawi Environmental Protection Agency
55Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMNyamagabe Integrated Climate Resilient Water Supply and Sanitation for Sustainable Job Creation and Economic GrowthWater For PeopleRwandaWater Supply and Sanitation$62m$37mResource Mobilization and Project implementation started in 2024.
56Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMOlifants-Doorn River Water Resources Project_Raising of Clanwilliam DamSouth Africa Department of Water and SanitationSouth Africa/ Western CapeRaw Water Resources$450m$450Construction is currently underway and at 22% complete.
57Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMOperationalization of Hydrometric Stations for Sao Tome and PrincipeProgramme for Infrastructure Development in Africa (PIDA)São Tomé and PríncipeEarly waring systems$1.5m$1.5mFeasibility study and rehabiliation works required
58Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMOptimizing Climate-smart Ag Practices through expansion of climate resilient irrigation integrated with small dam infrastructure and the recovery of floodwater and water resources in the Kayes regionAU AIP Multi-country GCF Readiness ProjectMaliIrrigation, water resource management (IWRM)$28m$2.5mConcept Note being developed
59Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMOuagadougou City Drinking Water Supply Project from the Ziga Dam Phase II, Tranche IIINationalBurkina FasoWater Supply$145.3m$145.3mFeasibility Study
60Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMPilot program for the implementation of IWRM in the Bandama basinNationalCote d'IvoireIWRM$80m$80mMaster Plan and EESS and environmental studies available
61Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMPremium Sustainable Aquaculture & Trout Farming ProjectLesotho Highlands Development AuthorityLesothoFisheries$42m$42mProof-of-Concept Operational, transitioning to Scale-Up & Value-Chain Expansion
62Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMProject for the Protection of Water Resources, Developments and Hydraulic Works in the Cavally BasinNationalCote d'IvoireIWRM$10m$10mFeasibility and environmental studies conducted
63Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMProject to build five new fecal sludge treatment plants (FSTPs) in the cities of Ouagadougou, Bobo-Dioulasso, Koudougou, and BanforaNationalBurkina FasoSanitation$38.3m$38.3mTechnical and environmental (EIES) study reports available
64Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMProject to establish a groundwater monitoring network in the four basins of Bandama, Sassandra Comoé and CavallyNationalCote d'IvoireWater Management$5m$5mStudies on monitoring groundwater resources conducted
65Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMProject to mobilize raw water for multiple purposesNationalCote d'IvoireWater supply, Irrigation, Livestock and Fish farming$65m$65mTechnical and environmental studies available
66Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMProject to strengthen the national water quality observation and monitoring networkNationalCote d'IvoireIWRM$18m$18mIdentification studies available
67Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMProject to Support the Strengthening of the resilience of ecosystems and vulnerable communities to climate change (PARREC) in the national portion of the Volta BasinNationalCote d'IvoireWater and flood management$8m$8mTechnical and environmental studies conducted
68Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMProtecting Kanyaru River watersheds using climate-informed ecosystem-based adaptation to support community resilienceAU AIP Multi-country GCF Readiness ProjectBurundiWatershed restoration, food security and sustainable livelihoods$50m$50mConcept Note being developed
69Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMProtection and Development of the coastal area from Sidi saber up to Al Silsila in front of Bibliotheca Alexandrina_ Alexandria governorateAIP Investment Action PlanEgyptFlood Protection€100m€100mProject Structuring
70Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMRaising of the Hawanee Dam to supply Mbabane with potable waterAfrica Water FacilityEswatiniMultipurpose€12.5 m€12.5 mInvestment ready
71Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMRehabilitation of fourteen (14) multipurpose reservoirsNationalCote d'IvoireIrrigation, Livestock and Fish Farming$12m$12mTechnical and environmental studies conducted
72Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMResilient Waters, Empowered Communities_Strengthening Integrated Water and Renewable Energy Systems through District-Level Climate Governance in Ghana.AU AIP Multi-country GCF Readiness ProjectGhanaClimate-resilient water management and integrated renewable energy systems$30m$30mConcept Note being developed
73Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMRuvyironza Multipurpose Water Resources Development ProjectAfrica Water FacilityBurundiMultipurpose dam and power generationTBDTBDProject pepration ongoing
74Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMSalima Lilongwe Water Supply CompanyNationalMalawiWater Supply$315m$215mConstruction phase commenced in January 2025
75Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMSouth Africa Municipal Non-revenue Water (“NRW”) ProgrammeSouth Africa DWS Water Partnerships OfficeSouth AfricaWater and Sanitation$500m$500mEthekwini Metro is the first pilot project, currently under implementation preparation Preparation and design phase across a pipeline of projects Various sub-projects in “Preparation” or “Preparing to procure TA” stages
76Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMSouth Africa Water Reuse Programme (“WRP”)South Africa DWS Water Partnerships OfficeSouth AfricaWater Supply and Sanitation (Wastewater Treatment and Reuse)$1.472Bln$1.472BlnProject definition, planning, pre-feasibility & bankable feasibility studies (2024–2033) Multiple sub-projects in various stages: RFP, feasibility, TA procurement, scoping
77Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMSouth African Non-Sewered Sanitation ProgrammeSouth Africa DWS Water Partnerships OfficeSouth AfricaSanitation$50m$50mProcurement is underway to develop a national strategy for scaling NSS using targeted municipalities.
78Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMSouthern African Development Community Regional Climate Resilient Water Investment Programme (SADC AIP)_Climate Resilient Hydrological Cycle Observation System for SADCAU AIP Multi-country GCF Readiness ProjectAngola, Botswana, eSwatini, Lesotho, Malawi, Mauritius, Mozambique, Namibia, Seychelles, South Africa, Tanzania, Zambia, ZimbabweWater$106.5m$106.5mConcept Note being developed
79Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMStrategic Actions for Climate Resilient Water Resources Management in the Orange-Senqu River BasinORASECOM Investment PipelineSouthern Africa (Botswana, Lesotho, Namibia, South Africa)Water Resources Management, Climate Resilience, Digital Infrastructure$23m$23mConcept Notes Developed and Approved by ORASECOM Council in July 2024
80Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMStrengthening the Climate Resilience of Vulnerable Communities in a Source-to-Sea approach, through Nature-Based Solutions in critical transboundary areas between Eswatini, Mozambique and South Africa.ANACMozambique, Eswatini and South AfricaWater Supply, Sanitation, Irrigation, Flood Management$35m$35mDesign phase
81Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMSupport "PACWA" and enhance institutional capacity building for professionals from Egypt and African countries in the water and climate sectors. (Pan-African Centre for Water and Climate Adaptation)NationalEgyptWater Management, Climate Adaptation, Capacity Building$8m$8mProject Preparation Stage (Start: Mar 2026, End: Sept 2029; pending funding)
82Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMSustainable Land and Water Resources Management in Arid and Semi-Arid Districts of Zambezi and Save River BasinsAU AIP Multi-country GCF Readiness ProjectMozambiqueWater$25m$25mConcept Note being developed
83Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMTeum Kourayeu - integration of traditional knowledge, inclusive practices and technologies for social peace and fisheries resilienceEquity FutureChadTraditional knowledge/water conflict resolution$0.8m$0.8mPilot phase completed; regional scale-up planned for the period December 2025 to November 2029
84Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMuMzimkhulu River Abstraction Wier and Pipeline (Cwabeni BWS)South Africa Department of Water and SanitationSouth Africa  (Kwa-Zulu Natal)Bulk Water Services Infrastructure DevelopmentZAR1.2BlnZAR1.2BlnFeasibility Study and Preliminary Design Report have been completed. Currently finalizing all the legislative requirements and the Implementation Readiness Study (i.e Detailed Bankable Feasibility Study). Will require some funding for planning ($ 1 086 62
85Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMUpgrading and Extension of Mwanza Water SupplyNationalMalawiWater Supply$42m$42mDesigns and contract documents are completed.
86Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMUsing Solar and Wind Energy to Extract Groundwater in the Pastoral Wells in the Western Region of the Jafara PlainProgramme for Infrastructure Development in Africa (PIDA)Libya and TunisiaIWRM$1.4m$1.4mGroundwater assessment undertaken - Requires feasibility study.
87Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMVaal Gamagara Bulk Water Supply extension (Phase 2)South Africa Department of Water and SanitationSouth Africa  (Northern Cape)Bulk Water Services Infrastructure DevelopmentZAR8.1BlnZAR8.1BlnFeasibility Study and Preliminary Design Report have been completed, however documents need some updating and the EIA, WULA and land agreements are outstanding. Currently updating the PDR and finalizing all the outstanding legislative requirements and the
88Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMWater Supply Project in Antanambao Manampotsy (Atsinanana Region)Programme for Infrastructure Development in Africa (PIDA)MadagascarWater Supply$4.2m$4.2mConcept Note developed
89Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMWestern Highveld Bulk Water SchemeSouth Africa Department of Water and SanitationSouth Africa  (Mpumalanga)Bulk Water Services Infrastructure DevelopmentZAR1.5BlnZAR1.5BlnFeasibility Study, Preliminary Design Report, all legislative requirements and the Implementation Readiness Study (i.e Detailed Bankable Feasibility Study) have all been completed. Requires funding for implementation. 
90Satsiri Winberg11/08/2025 09:14 AMSatsiri Winberg11/08/2025 09:14 AMAIP Water Investment Scorecard ImplementationAIP Investment Action PlanContinentalEnabling Environment project - Governance$30m$30mImplementation